CONSTRUCTION-RELATED INFORMATION

The preconstruction phase generally begins after the construction drawings and specifications have been completed and culminates in the selection of the construction team. The construction of even a small building involves so many specialized skills and trades that the work cannot normally be undertaken by a single construction firm. Instead, the work is generally done by a team consisting of the   general contractor  and a number of specialty subcontractors .

Thus, a project may have roofing; window and curtain wall; plumbing; and heating, ventilation, and air-conditioning (HVAC) subcontractors, among others, in addition to the general contractor. The general contractor’s own work may be limited to certain components of the building (such as the structural components—load-bearing walls, reinforced concrete beams and columns, roof and floor slabs, etc.), with all the remaining work subcontracted.

In contemporary projects, however, the trend is toward the general contractors not performing any actual construction work but subcontracting the work entirely to various sub-contractors. Because the subcontractors are contracted by the general contractor, only the general contractor is responsible and liable to the owner.

In some cases, a subcontractor will, in turn, subcontract a portion of his or her work  to another subcontractor, referred to as a   second-tier subcontractor, Figure 1.6. In  that  case, the general contractor deals only with the subcontractor, not the second-tier subcontractor.

Whether the general contractor performs part of the construction work or subcontracts  the entire work, the key function of the general contractor is the overall management of  construction. This includes coordinating the work of all subcontractors, ensuring that the  work done by them is completed in accordance with the contract documents, and ensuring  the safety of all workers on the site. A general contractor with a good record of site safety  not only demonstrates respect for the workers but also improves the profit margin by lowering the cost of construction insurance.

  FIGURE 1.6  Members of the construction team and their interrelationships with each other and
the owner. A solid line in this illustration indicates a contractual relationship between parties. A
dashed line indicates a communication link, not a contract. The relationships shown here are not
absolute and may change with the nature of the project.

0 comentarios:

Post a Comment